Elmhurst Park District News

Posted: July 5, 2013

The Wilder Park Conservatory and Greenhouse Restoration Project continues; the frames for the foundations have been removed and construction crews have begun to backfill the spaces surrounding the foundations.

Posted: June 28, 2013

The Wilder Park Conservatory and Greenhouse Restoration Project is starting to take shape-literally. The framings for the foundations of the Greenhouse and Propagating House were completed and the new foundations were poured.

Posted: June 14, 2013

The Wilder Park Conservatory & Greenhouse Restoration Project continues to progress. The panes of glass lining the Conservatory structure have been completely removed, leaving behind the bare frame. The boiler room has also been cleared out, paving the way for new, efficient HVAC systems.

Posted: February 25, 2013

The Landscape Architect & Specifier News is featuring Elmhurst’s very own Berens Park West Playground in its March 2013 issue.