Wagner Community Center (WCC) Project

  • WCC Design Development Task Force:
    • Dewberry met with program supervisors and key staff to discuss their respective areas in the new center and further refine the details for specific programming spaces.
    • Dewberry met with IT staff to discuss networking, security, building access, etc.
    • Dewberry met with operations staff to review HVAC and mechanical systems.
  • Construction Management Firm Selection Process:
    • Following selection of McHugh+Nacional, began negotiations on a contract for construction management services.
  • WCC Relocation Task Force:
    • Investigation into potential lease options for commercial space to accommodate the District’s gymnastics and dance programs is ongoing.

Community Engagement & Communications

  • Community Engagement & Communications Task Force:
    • Updated District website referendum pages to include individual referendum project progress reporting and timelines along with reorganized and updated FAQs.

Crestview Park Master Plan

  • Hosted Master Plan Open House on March 20 (75 attendees) to provide residents an opportunity to share their future vision for the Park.
  • V3 assessing community input, suggestions, feedback, etc., to begin developing draft Master Plan concepts.
  • Second Open House to share the concepts with the community scheduled for May 1.

Wilder Park Bandshell with Restrooms

  • Staff met with Upland Design to discuss Master Planning process for Wilder Park southside, including community engagement