April 2026 Referendum Progress Report

  • Progress Report

Wagner Community Center (WCC) Project

  • Silt fencing and tree protection measures installed.
  • Excavation, including asphalt removal, soil stripping, and footing excavation, underway along with site utility work.
  • RFQ issued to solicit qualified firms for building commissioning services.
  • Board approved bids for glulam beams and metal panels; rejected bid for fireproofing.
  • Fifth package let for bid including fireproofing, gym equipment, numerous flooring surfaces, millwork, and overhead doors with bids opened on April 9.

Wilder Park Bandshell with Restrooms

  • Board approved funding for non-referendum Master Plan components to accompany bandshell and restrooms.
  • Board approved architectural & engineering services contracts with Upland Design and Dewberry Architects for implementation of the Wilder Park South Master Plan and recreation building redevelopment.

Restroom Buildings

  • Eldridge Park - Ribbon Cutting held on April 11.
  • Crestview Park – Board approved facility design.
  • Prairie Path - Board approved facility design and staff had a second meeting with DuPage County Division of Transportation to discuss location.