Wagner Community Center (WCC) Project
- Excavation and concrete pours for foundations in all four main areas completed.
- Delivery and installation of StormTrap stormwater management system complete with backfilling over geotechnical fabric ongoing.
- Furniture manufacturer visit conducted with Dewberry interior design professionals and held recap meeting.
Crestview Park and Prairie Path Restroom Buildings
- Presented to the City of Elmhurst Zoning and Planning Commission on July 21.
- Crestview - Conditional Use Permit
- Prairie Path - Setback Variance
- Issued for bid on July 29.