December 2025 Referendum Progress Report

  • Referendum Progress Report

Wagner Community Center (WCC) Project

  • Final Planned Unit Development approved by City of Elmhurst Development, Zoning, and Planning Committee.
  • Facility electricity disconnected and site fenced and secured. Detour erected to notify path users of certain path closures.
  • Board approved contract for Precast Concrete.
  • Bid packages issued for HVAC, Plumbing, Electrical, Fire Protection, Excavation, Site Utilities, Structural Steel, and Cast-in-Place-Concrete.
  • Facility demolition underway; community groundbreaking held on December 6.

Wagner Community Center (WCC) Relocation

  • Gymnastics and dance programs began at 185 Industrial Drive on December 1.

Eldridge Park Restroom Building

  • Brickwork, rough electrical, and plumbing work inside the building, roofing is complete.

Wilder Park Bandshell with Restrooms

  • On November 6,425 postcards announcing the November 20 open house mailed to homes in the vicinity of Wilder Park and communicated on social media and website.
  • Open House held November 20 at Wilder Mansion to coincide with launch of Wilder Park South Concept Plans survey (approx. 60 attended).
  • Sent targeted e-blast to District database, included in December District e-newsletter and distributed press release to the newspapers.
  • Survey closed on December 1.

Prairie Path Restroom Building

  • Survey results will be analyzed and findings presented at a future Board meeting.