Wagner Community Center (WCC) Project
- Final Planned Unit Development approved by Elmhurst City Council.
- Board approved Guaranteed Maximum Price with McHugh+Nacional.
- Board approved bids for Excavation, Site Utilities and Cast-in-Place Concrete.
- Facility demolition substantially complete.
Eldridge Park Restroom Building
- Construction complete; awaiting ComEd connection of permanent electrical service to the building.
Wilder Park Bandshell with Restrooms
- Staff presented summary findings of the Wilder Park South Master Plan community survey feedback.
- Board discussed proposed next steps for January 12, 2026 meeting to consider formal motions and vote on individual park components in a format similar to survey.
Prairie Path Restroom Building
- Survey results will be analyzed and findings presented at a future Board meeting.