July 2026 Referendum Progress Report

Elmhurst Park District logo next to Elmhurst Votes Yes logo in speak bubble graphic.

Wagner Community Center (WCC) Project

  • Sixth bid package approved by Board including Wood Flooring, Interior and Exterior Painting, Site Concrete, Landscaping and Irrigation, Asphalt and Paving, Fencing and Gates, Site Furnishings/Flagpole, and Playground Equipment.
  • Six proposals submitted for Building Enclosure Commissioning.
  • Delivery and installation of StormTrap stormwater management system more than 50% complete.
  • Kick-off meeting with Dewberry interior design professionals held concerning furniture selection.

Wilder Park Bandshell and Restroom Building

  • Soil sampling completed (8 total borings).

Prairie Path Restroom Building

  • Permits filed with City of Elmhurst and DuPage County.
  • Soil sampling completed (2 total borings).
  • Underground utility locating completed.
  • July 21 zoning hearing required notification posted.

Crestview Park Restroom Building

  • Permit filed with City of Elmhurst.
  • July 21 zoning hearing required notification posted.