March 2025 Referendum Progress Report

  • Referendum Progress Report

March 2025 Progress Report

Financials

  • Bond closing took place on February 18 when $89,950,000 was wired to the District's new investment account with PFM

Wagner Community Center (WCC) Project

  • WCC Design Development Task Force:
    • met with representatives of the City to further discuss permitting and zoning requirements for each of the referendum projects, including Wagner Community Center
    • met twice to review floor plans, sites plans, and building images
  • Construction Management Firm Selection Process:
    • eleven construction management qualification proposals submitted by the February 7 deadline
    • submittals reviewed and evaluated by staff and Dewberry
    • three firms interviewed by staff and Dewberry
  • WCC Relocation Task Force:
    • finalized existing spaces that are available within the District
    • determined what other spaces (non-District) are needed to house programs/services
    • began making inquiries into potential lease options for commercial space to accommodate the District’s gymnastics and dance programs

Community Engagement & Communications

  • Reviewed current and potential strategies for external customers and internal staff
  • Drafted timeline for community engagement for referendum projects

Crestview Park Master Plan

  • Site inventory and analysis completed by V3
  • Baseline and existing inventory plan completed
  • Master Plan Public Open House scheduled for March 20, 2025