March 2026 Referendum Progress Report

  • Referendum Progress Report

Wagner Community Center (WCC) Project

  • Tree clearing completed onsite in advance of start of excavation and underground site utilities.
  • Board approved Bid Package #3 - Masonry, Miscellaneous Metals, Cold Formed Metal Framing - Drywall, Roofing, Curtain Wall, and Elevator.
  • Construction trailer situated on site.
  • Temporary power being connected.
  • Fourth package let for bid including Glulam Beams and Fireproofing with bids opened on February 27.

Wilder Park Bandshell with Restrooms

  • Board approved Wilder Park South Master Plan including redevelopment of existing Recreation Building for restrooms.
  • Staff identified funding for non-referendum Master Plan components.

 Eldridge Park Restroom Building

  • Electricity connected to facility by ComEd.
  • Facility passed final inspections and opened on March 9.