Wagner Community Center (WCC) Project
- Underground utility work taking place, including establishment of new water service from West Avenue.
- Fifth bid package approved by Board, including Fireproofing, Gym Equipment, Numerous Flooring Surfaces, Millwork, and Overhead Doors.
- Eight proposals submitted for building commissioning.
- Sixth package let for bid including Wood Flooring, Interior and Exterior Painting, Site Concrete, Landscaping and Irrigation, Asphalt and Paving, Fencing and Gates, Site Furnishings/Flagpole, and Playground Equipment with bids to be opened on May 21.
- Quarterly update mailed to nearby neighbors.
Wilder Park Bandshell with Restrooms
- Design development phase on-going, including technology needs.
- Preliminary Planned Unit Development (PUD) application submitted to City of Elmhurst.
- Required PUD public meeting scheduled for Thursday, May 21, 2026 from 5:30 to 7:00 pm at the Wilder Mansion; with notices mailed to 160 properties within 500 feet of Wilder Park from a list of addresses provided by the City.
Restroom Buildings
- Prairie Path - Board approved revised location closer to Path.