November 2025 Referendum Progress Report

  • Referendum Progress Report

Wagner Community Center (WCC) Project

  • Preliminary Planned Unit Development for project approved by Elmhurst Development, Zoning, and Planning Committee and City Council.
  • Coordination meeting held with ComEd to discuss demolition, temporary power, and new service to the new Wagner Community Center.
  • First two bid packages for the project issued for bid –Demolition and Precast Concrete.
  • Board approved contract for Demolition.

Wagner Community Center (WCC) Relocation

  • Main registration office operations shifted to the Kies Recreation Center.
  • Existing Wagner Community Center closed on October 19.
  • Specialized moving contractor relocated gymnastics equipment followed by a general moving contractor transferring all supplies, office furniture, and recreational equipment.
  • Recreation staff offices transitioned to 185 Industrial Drive.

Eldridge Park Restroom Building

  • Landscape restoration completed in areas where underground utilities were installed.
  • Brickwork, rough electrical, and plumbing work inside the building are ongoing.

Wilder Park Bandshell with Restrooms

  • Upland developed and presented concept plans with three bandshell locations.
  • Dewberry presented four bandshell designs for consideration.
  • Board reduced concept plan options to two - one east of Wilder Mansion and one facing north from what is considered the old ice-skating area.
  • Upland Design presented, and Board discussed, draft survey questions.
  • On Thursday, November 20 an Open House will be held from 5:30-7:00 p.m. at Wilder Mansion to coincide with the launch of survey.

Prairie Path Restroom Building

  • Approximately 20 residents attended the Public Open House held on October 21 at Wilder Mansion.
  • Survey available online from October 22 through November 4; 1,025 surveys submitted.
  • Survey results will be analyzed and findings presented at a future Board meeting.