Wagner Community Center (WCC) Project
- Light pole installation in main parking lot – complete
- Binder coat/course paving in main parking lot – complete
- Parking lot curbs and islands in main parking lot – complete
- Structural steel – ongoing
- Roof installation over gymnasium, dance studio, and offices –ongoing
- Underground utilities – ongoing
Berens Park Artificial Turf Field
- Exterior curb installation – complete
- Stone sub-base installation – complete
- Fencing and sports netting installation – underway
- FieldTurf installation – underway
Wilder Park Bandshell and Restroom
| Date | Milestone | Details |
|---|---|---|
| August 25 | Initial Hearing | District requested a Conditional Use Permit for a Preliminary Planned Unit Development (PUD); Commission raised questions about the project |
| October 6 | Responses Presented | Staff, Dewberry, and Upland Design answered the Commission’s questions |
| October 6 | Hearing Continued | Commission suggested guidelines be established for bandshell operation |
| Ongoing | Staff Follow-Up | Staff to discuss bandshell operating guidelines with City staff |
| November 10 | Continued Hearing | Commission resumes review of the PUD request |
Prairie Path Restroom Building
- Masonry work – complete
- Roof installation – complete
- Electrical work – underway
Crestview Park Restroom Building
- Underground utilities – complete
- Concrete foundation – complete
- Masonry work – underway