Wagner Community Center (WCC) Project
- Structural steel – underway
- Roof over dance studio and offices – underway
- Underground utilities – underway
- Parking lot light pole bases – complete
- Parking lot curbs and islands – underway
- Turf field stone sub-base – underway
Wilder Park Bandshell and Restroom
| Date | Milestone | Details |
|---|---|---|
| August 25 | Initial Hearing | District requested a Conditional Use Permit for a Preliminary Planned Unit Development (PUD); Commission raised questions about the project |
| October 6 | Responses Presented | Staff, Dewberry, and Upland Design answered the Commission’s questions |
| October 6 | Hearing Continued | Commission suggested guidelines be established for bandshell operation |
| Ongoing | Staff Follow-Up | Staff to discuss bandshell operating guidelines with City staff |
| October 20 | Continued Hearing | Commission resumes review of the PUD request |
Prairie Path Restroom Building
- Construction and silt fence erected.
- Excavation and water and sanitary pipe installation completed.
- Concrete foundation walls and floors poured.
- Backfilling completed in and around the foundation.
- Sidewalk connecting the 9/11 Memorial to Spring Road
Crestview Park Restroom Building
- Construction and silt fence erected.
- Excavation underway
