A permanent, heated restroom at Crestview Park will give park users access to safe, clean restrooms year-round.
This project falls under the Elevate Elmhurst Parks Priority of Invigorated Parks.
Latest Progress Report
- Construction permits filed.
- Both projects approved by the City of Elmhurst Zoning and Planning Commission, Development, Planning and Zoning Committee, and City Council.
- Crestview - Conditional Use Permit
- Prairie Path - Setback Variance
- Issued for bid on July 29 and recommended contractors will be brought to Park Board on September 14.
2026 Mid-Year Progress Report
A new Master Plan for Crestview Park was approved in 2025. The plan includes a permanent heated restroom building, with construction expected to begin this fall as part of Phase 1 improvements at the park.
Milestone Timeline (subject to change)
- Winter 2026: Begin design development and permitting for Crestview Park restroom building
- Spring 2026: Begin design development and permitting for Crestview Park restroom building
- Summer 2026: Complete design development and permitting for Crestview Park restroom building, begin construction of Crestview Park restroom building
- Fall 2026: Begin construction of Crestview Park restroom building
- Winter 2027: Complete construction