Work continues at Butterfield Park. Demolition is underway with most of the paths removed.  All of the fencing has been removed from ballfields 2,3 and 4 as well as the asphalt around the fields.  The surfacing of the tennis courts has been removed, as well as the fencing.  The excavation for the drainage and sewer improvements is scheduled to begin next week, but is weather dependent.  The playground is moving along quickly with most of the 5-12 structure assembled and standing.  Laying out of the zipkrooz began today and work on the underdrain will begin next week. Click here to see the design plans for Butterfield Park and to learn more about the Playground for Everyone.