Progress continues at 185 Industrial Drive, which will serve as the temporary home of dance and gymnastics programs while Wagner Community Center is under construction.

Drywall installation is nearing completion; next steps will be to prime and paint followed by installation of the ceiling grid. Most of the electrical and HVAC is connected and scheduled to be tested and started up this week.

Wagner programs will continue at their current location through October 19. After that, Park District staff will move into 185 Industrial Drive and prepare for the second session of fall programs, which will begin December 1.

Keep an eye out for information on a groundbreaking at Wagner Community Center later this fall! For updates on all referendum projects, please visit epd.org/referendum.