In 2024, staff propose completing Phase 2 of a three-year project to replace WCC flooring originally installed in 1961 and showing signs of deterioration and cracking in specified areas. Phase 2 includes updating the old flooring with high-end vinyl sheet flooring in multipurpose rooms B, C, D and corridors for $80,000. Spreading the cost of the project over three years allows for isolation of certain building sections to be closed at one time, minimizing interruptions to programs and services. The floor is known to have asbestos containing material mastic due to its age so the project includes abatement ($40,000) to remove hazardous materials safely before installation of the new flooring ($40,000). In 2023, Phase 1 included the areas in the graphic below for $99,000 and Phase 3 is anticipated to cost $92,200 in 2025. This proposed project will be funded with Recreation Fund reserves ($80,000).