Construction on the Marjorie Davis Garden Plots has been moving slowly due to the extremely wet conditions on the site, but progress is occurring despite the circumstances. The water lines and yard hydrants have been installed. Grading and soil amending is on-going. Perimeter restoration work will begin the week of May 28 as well as fence installation. The target date for opening the plots has been moved to June 9.
The 2017 Marjorie Davis Garden Plot Project is underway. The construction and silt fencing has been installed and the tree removal has been completed. The stumps are being ground and the west portion of the site is being cleared of debris and old plant material.