Berens Park Tennis Courts Replacement (2026)

Outdoor tennis court with green hard surface, white lines, and a black tennis net. Shade structures and bleachers are in the background.
Refinished tennis courts
Outdoor tennis court with green playing surface, white boundary lines, and chain-link fencing, viewed from the sideline with tall light poles and shade structures in the background.
Refinished tennis courts
Cracked pavement in between two tennis courts
Previous Berens Park Tennis Courts conditions
Aerial view of tennis court asphalt surrounded by a black fence.
Fence fabric and gates installation
Progress
Project Complete
Anticipated Completion Date
August 2026
Project Budget
$1,643,300
Project Summary

The twelve tennis courts at Berens Park show significant signs of wear and age. An overlay acting as a stop-gap measure to correct cracking in the original asphalt surface was installed in 2004 while the current slip sheet asphalt surface was added in 2017. Current conditions show cracking emanating from both the original and slip sheet surface installation. The work completed previously was not inadequate, but the frequency of use, existing conditions, weather, and current construction methodology will require the facility to be demolished to the sub-surface and reconstructed from the ground up. 

Due to the condition of the tennis courts, staff propose budgeting to replace the six north and six south courts and the promenade area (walking and viewing area around courts) as well as replacing the lighting and fencing. Considering the location and age of the current lighting system on the six south courts, there is an opportunity to address these issues while the court and promenade surface is being removed. The lighting upgrades include removing the light poles currently inside the courts and placing them outside the courts, eliminating a potential safety issue. 


This project falls under the Elevate Elmhurst Parks Priority of Invigorated Parks
Tactic:  Replace Berens Park Tennis Courts

Project News

Updated Thursday, October 1, 2026 - 11:12am

Ribbon cutting celebrates refreshed tennis courts at Berens Park

Elmhurst Park District Board members and staff commemorated the newly redeveloped Berens Park tennis courts with a ribbon cutting last Friday, September 18. After wrapping up their team practice, the York Community High School Girl’s Tennis Team also joined in the celebration.

Updated Monday, September 21, 2026 - 7:56am

Berens Park tennis court ribbon cutting on September 18

The Berens Park tennis courts bounced back into action this month and we’re celebrating with a ribbon cutting! Join Elmhurst Park District on Friday, September 18 at 6pm to commemorate the redevelopment of the courts.

Updated Thursday, September 10, 2026 - 12:44pm

Berens Park tennis courts reopening Tuesday, September 1

The Berens Park tennis court project is wrapping up. Finishing touches are being completed and the courts will reopen on Tuesday, September 1 to the public.

Updated Monday, July 13, 2026 - 8:31am

Lighting installation underway at Berens Park Tennis Courts project

Checking in at the Berens Park Tennis Courts project - New light poles were installed for the South Courts. The light poles have been relocated to outside the fence line to improve safety and functionality.

Updated Monday, June 29, 2026 - 7:14am

Asphalt installation begins at Berens Park Tennis Courts

Progress at the Berens Park Tennis Court Replacement continues with installation of the initial asphalt base. Courts will receive additional asphalt layers and finish with a color coat for a great playing surface. 

Next steps in the project will be the installation of lamp posts and chain link fencing for the courts.

Updated Tuesday, April 7, 2026 - 5:02pm

Berens Park Tennis Courts Replacement project underway

The Berens Park Tennis Courts Replacement project is now underway as demo has begun.

Construction fence and silt fence is up and will remain up for the duration of the project. For visitor safety, the pathway along Oaklawn Ave adjacent to the tennis courts will be closed until project completion. The asphalt pathway will be fully renovated as part of the project.