Plunkett Park Playground Work Continues with Equipment Installation

  • Plunkett Park
  • Plunkett Park

Work on the redevelopment of Plunket Park playground is moving swiftly. Most of the concrete has been poured, which will allow for the installation of new picnic tables, and equipment installation has begun. The 2-5 years olds structure is going up as well as the swing structure. Nature inspired elements, including a log replica tunnel, are being installed as well. The project is still on track to be completed by October 2017. Visit the Plunkett Park playground project page for ongoing updates and more information.