A permanent, heated restroom along the Prairie Path will give park users access to safe, clean restrooms year-round.
This project falls under the Elevate Elmhurst Parks Priority of Invigorated Parks.
Latest Project Report
- Permits filed with City of Elmhurst and DuPage County.
- Soil sampling completed (2 total borings).
- Underground utility locating completed.
- July 21 zoning hearing required notification posted.
2026 Mid-Year Progress Report
The Park Board approved the Prairie Path restroom location following a public open house and survey. It will be located along Spring Road near the gazebo. Pre-construction activities, including permit submissions to the City of Elmhurst and DuPage County and underground utility locating, are complete. Construction is expected to begin this fall and wrap up in early 2027.
Milestone Timeline (subject to change)
- Winter 2026: Staff recommend, and Board approve, location of Prairie Path restroom
- Spring 2026: Begin design and permitting for Prairie Path restroom building
- Summer 2026: Complete design and permitting for Prairie Path restroom building
- Fall 2026: Begin construction of Prairie Path restroom building
- 2027: Complete construction of Prairie Path restroom building
