Permanent heated restroom in Eldridge Park

  • Eldridge Park year-round restroom
    Eldridge Park year-round restroom location and design
  • Groundbreaking on September 13, 2025
    Groundbreaking on September 13, 2025
Progress
Project Started
Anticipated Completion Date
2025
Project Budget
$500,000
Project Summary

A permanent, heated restroom at Eldridge Park will give park users access to safe, clean restrooms year-round. 

This project falls under the Elevate Elmhurst Parks Priority of Invigorated Parks.

Project Progress

 

Latest Project Report

  • Mandatory pre-bid meeting for the project held on August 12 with 24 contractors in attendance.
  • Bids opened on August 26.
  • A groundbreaking at the project site to be held on Saturday, September 13.

Milestone Timeline (subject to change)

  • Summer 2025: Complete bid process and begin construction of Eldridge Park restroom building
  • Fall 2025: Complete construction of Eldridge Park restroom building

Project News

Updated Tuesday, September 16, 2025 - 11:47am

Park District referendum projects kickoff with groundbreaking at Eldridge Park Restroom Building

A rainy morning didn’t dampen the mood of those gathered at Eldridge Park last weekend.

Updated Sunday, September 14, 2025 - 5:15pm

Eldridge Park Restroom Building Groundbreaking

Elmhurst Park District is breaking ground on the Eldridge Park Restroom Building. The project is part of the Elmhurst Park District Referendum, which passed in November 2024.