The new Wagner Community Center will accommodate more residents and feature:
- Free three-lane walking/jogging track
- Gymnasium for pickleball, basketball, volleyball and other sports
- Artificial turf field for soccer, football, baseball and other sports
- Larger spaces for dance and gymnastics programs
- Flexible multi-purpose spaces for more programming and community gatherings
- Indoor play area for children
- Dedicated early childhood and preschool spaces with a secure entrance
This project falls under the Elevate Elmhurst Parks Priority of Vibrant Facilities.
Latest Project Report
Wagner Community Center (WCC) Project
- Silt fencing and tree protection measures installed.
- Excavation, including asphalt removal, soil stripping, and footing excavation, underway along with site utility work.
- RFQ issued to solicit qualified firms for building commissioning services.
- Board approved bids for glulam beams and metal panels; rejected bid for fireproofing.
- Fifth package let for bid including fireproofing, gym equipment, numerous flooring surfaces, millwork, and overhead doors with bids opened on April 9.
Milestone Timeline (subject to change)
- Winter 2026
- Complete WCC demolition and begin site clearing, excavation, and foundations
- Spring 2026
- Complete WCC precast wall panel installation
- Summer 2026
- Complete WCC steel erection, WCC underground utilities, and WCC structural slabs/concrete
- Fall 2026
- Complete WCC exterior enclosures and elevator installation, begin WCC interior framing, MEP (mechanical, electrical, plumbing) rough-in, interior finishes, and sitework.
- 2027
- Complete WCC construction
- Move out of temporary spaces and into WCC
- WCC grand opening and begin offering programs