New Wagner Community Center

  • New Wagner Community Center
Progress
Project Started
Anticipated Completion Date
2027
Project Budget
$84,950,000
Project Summary

The new Wagner Community Center will accommodate more residents and feature: 

  • Free three-lane walking/jogging track
  • Gymnasium for pickleball, basketball, volleyball and other sports
  • Artificial turf field for soccer, football, baseball and other sports
  • Larger spaces for dance and gymnastics programs
  • Flexible multi-purpose spaces for more programming and community gatherings
  • Indoor play area for children
  • Dedicated early childhood and preschool spaces with a secure entrance

This project falls under the Elevate Elmhurst Parks Priority of Vibrant Facilities.

Project Progress

Latest Project Report

  • Wagner Community Center (WCC) Project
    • Dewberry, McHugh+Nacional and staff conducted the first of the weekly Owner Architect Contractor (OAC) preconstruction meeting.
    • Park Board reviewed and approved exterior elevations for new facility.
    • WCC abatement project package was issued for bid; mandatory pre-bid meeting held on-site and bids opened on May 27.
    • Notice of June 11 neighborhood meeting sent to property owners within 500 feet of WCC as part of Planned Unit Development process.
  • Wagner Community Center (WCC) Relocation
    • Completed negotiations on terms and attorneys drafted lease agreement for proposed location at 185 Industrial Drive.
    • Board approved three-year lease.

Milestone Timeline (subject to change)

  • Spring 2025:
    • Complete WCC relocation plan
    • Complete WCC design development and construction documents and Board approve design
  • Summer 2025
    • Move out of WCC
  • Fall 2025
    • Relocate WCC Programs
    • Begin WCC abatement
    • Demolish WCC
    • Complete WCC bid process
    • Begin WCC construction
  • 2027
    • Complete substantial WCC Construction
    • Move out of temporary spaces and into WCC
    • WCC grand opening and begin offering programs

Project News

Updated Friday, June 27, 2025 - 3:43pm

Wagner Community Center Project moves forward with design and temporary relocation plans

At their June 9 Park Board meeting, the Elmhurst Park District Board of Park Commissioners approved the exterior elevations for the new Wagner Community Center, taking another big step forward in the realization of one of the District’s most significant redevelopment projects.

Updated Wednesday, June 4, 2025 - 10:21am

With Wagner construction expected to begin this fall, Park District makes plans to temporarily move programs

Design development for the new Wagner Community Center is moving along at the Park District, but another key component of the project is also taking shape - where programs will move while construction takes place.

Updated Thursday, May 1, 2025 - 12:46pm

Plans for new Wagner Community Center taking shape

The Board of Park Commissioners reviewed and approved the schematic design for the new Wagner Community Center at their Monday, April 14 Park Board meeting.