New Wagner Community Center

  • New Wagner Community Center
Progress
Project Started
Anticipated Completion Date
2027
Project Budget
$84,950,000
Project Summary

The new Wagner Community Center will accommodate more residents and feature: 

  • Free three-lane walking/jogging track
  • Gymnasium for pickleball, basketball, volleyball and other sports
  • Artificial turf field for soccer, football, baseball and other sports
  • Larger spaces for dance and gymnastics programs
  • Flexible multi-purpose spaces for more programming and community gatherings
  • Indoor play area for children
  • Dedicated early childhood and preschool spaces with a secure entrance

This project falls under the Elevate Elmhurst Parks Priority of Vibrant Facilities.

Project Progress

 

Latest Project Report

Wagner Community Center (WCC) Project

  • Planned Unit Development for project approved by Elmhurst Planning and Zoning Commission and forwarded to Development, Zoning, and Planning Committee of the City Council.
  • Construction documents 95% complete.
  • Elmhurst City Council approved a vacation of a portion of Crockett Avenue to the Park District to facilitate construction of the new facility.
  • First two bid packages for the project, Demolition and Precast Concrete, issued for bid with a scheduled opening on October 10.

Wagner Community Center (WCC) Relocation

  • 185 Industrial Drive Rental Property
    • Rooftop HVAC units installed.
    • Drywall installation for gymnastics and dance area nearly complete.
    • Packing begun for move-out from existing community center.

Milestone Timeline (subject to change)

  • Spring 2025:
    • Complete WCC relocation plan
    • Complete WCC design development and construction documents and Board approve design
  • Summer 2025
    • Move out of WCC
  • Fall 2025
    • Relocate WCC Programs
    • Begin WCC abatement
    • Demolish WCC
    • Complete WCC bid process
    • Begin WCC construction
  • 2027
    • Complete WCC construction
    • Move out of temporary spaces and into WCC
    • WCC grand opening and begin offering programs

Project News

Updated Tuesday, November 4, 2025 - 1:50pm

185 Industrial Drive construction closing in on finish line

Things are really coming together at 185 Industrial, which will serve as the temporary home of dance and gymnastics programs while Wagner Community Center is under construction.

Dance lights are installed, ballet bars and mirrors are also in, HVAC system started up and all furniture and gymnastics equipment is moved into the building.

Updated Monday, November 3, 2025 - 1:47pm

Moving day at Wagner Community Center!

So many memories - so much more to come! The last day of programs was October 19 at Wagner Community Center. Since then, staff and moving crews have begun emptying the building of furniture and equipment to make way for construction fencing, which will go up in November.

Updated Tuesday, November 4, 2025 - 1:50pm

Wagner Community Center is now closed due to construction on the new facility

The facility's final day of operation was Sunday, October 19. It closed for construction on Monday, October 20.

Updated Friday, October 24, 2025 - 1:07pm

Progress Update at 185 Industrial Drive

Progress continues at 185 Industrial Drive, which will serve as the temporary home of dance and gymnastics programs while Wagner Community Center is under construction.

Updated Thursday, September 18, 2025 - 8:57pm

Progress Update: Staff prepping 185 Industrial Drive facility to welcome participants beginning December 1

Exciting progress is underway as the Elmhurst Park District prepares for the construction of a new, modern Wagner Community Center.

Updated Monday, July 14, 2025 - 9:47am

Wagner Community Center Project moves forward with design and temporary relocation plans

At their June 9 Park Board meeting, the Elmhurst Park District Board of Park Commissioners approved the exterior elevations for the new Wagner Community Center, taking another big step forward in the realization of one of the District’s most significant redevelopment projects.

Updated Monday, October 20, 2025 - 9:41am

Wagner Community Center program relocation

We’re thrilled to share that construction at Wagner Community Center will begin soon as we take the next step in Elevating Elmhurst Parks!

To keep programs running smoothly during construction, most Wagner programs and services will be relocated to other Elmhurst Park District facilities this fall. We’re also excited to announce that dance and gymnastics programs will have a new home at a newly-leased space at 185 Industrial Drive in Elmhurst—just down the street from Mariano’s!

Updated Wednesday, July 9, 2025 - 11:37am

With Wagner construction expected to begin this fall, Park District makes plans to temporarily move programs

Design development for the new Wagner Community Center is moving along at the Park District, but another key component of the project is also taking shape - where programs will move while construction takes place.

Updated Thursday, May 1, 2025 - 12:46pm

Plans for new Wagner Community Center taking shape

The Board of Park Commissioners reviewed and approved the schematic design for the new Wagner Community Center at their Monday, April 14 Park Board meeting.