The new Wagner Community Center will accommodate more residents and feature:
- Free three-lane walking/jogging track
- Gymnasium for pickleball, basketball, volleyball and other sports
- Artificial turf field for soccer, football, baseball and other sports
- Larger spaces for dance and gymnastics programs
- Flexible multi-purpose spaces for more programming and community gatherings
- Indoor play area for children
- Dedicated early childhood and preschool spaces with a secure entrance
This project falls under the Elevate Elmhurst Parks Priority of Vibrant Facilities.
Latest Project Report
- Excavation and concrete pours for foundations in all four main areas completed.
- Delivery and installation of StormTrap stormwater management system complete with backfilling over geotechnical fabric ongoing.
- Furniture manufacturer visit conducted with Dewberry interior design professionals and held recap meeting.
2026 Mid-Year Progress Report
Construction on the new facility began in late 2025. During the winter and spring, the former building was demolished, site clearing and excavation were completed, and underground utility installation got underway.
Concrete foundations for the building's precast panels were poured during the summer. The building will really begin taking shape as the precast panels are erected later this summer. These panels will form the exterior walls of the gymnastics center, indoor turf field, and gymnasium. The facility remains on schedule for completion in Fall 2027 as well as within budget.
Milestone Timeline (subject to change)
- Winter 2026
- Complete WCC demolition and begin site clearing, excavation, and foundations
- Spring 2026
- Complete WCC precast wall panel installation
- Summer 2026
- Complete WCC steel erection, WCC underground utilities, and WCC structural slabs/concrete
- Fall 2026
- Complete WCC exterior enclosures and elevator installation, begin WCC interior framing, MEP (mechanical, electrical, plumbing) rough-in, interior finishes, and sitework.
- 2027
- Complete WCC construction
- Move out of temporary spaces and into WCC
- WCC grand opening and begin offering programs



